Schemes to achieve solar power generation targets during phase II of JNNSM

- Advertisement -

The Ministry of New and Renewable Energy (MNRE) has proposed several strategies to promote the implementation of solar power projects under phase II of the Solar Mission

By EB Bureau

Tuesday, January 07, 2014: Phase II (2012-17) of the Jawaharlal Nehru National Solar Mission (JNNSM) focuses on installations for 10 GW of utility scale solar power, 1GW off-grid solar power projects, and the generation of 10 GW of grid-connected solar power, as it targets adding 20 GW of grid-connected and 2 GW of off-grid capacity by 2022, to be completed in three phases.

- Advertisement -

There are several strategies that have been proposed by the MNRE to meet these goals. The main schemes are—the bundling scheme; generation-based incentives; and viability gap funding.

Bundling scheme

The concept of bundling was introduced in phase I to facilitate grid-connected solar power generation. Solar power, which was still relatively expensive when this scheme was conceived, was bundled with conventional power from the unallocated quota generated at the National Thermal Power Corporation’s (NTPC) coal-based stations and was sold out to the distribution utility. The bundling concept was introduced to keep the cost of bundled power at approximately Rs 5/kWh. This proved to be a successful implementation strategy during Phase I, and the same is expected in phase II of JNNSM. The only disadvantage of this mechanism is the limited availability of conventional power from the unallocated central pool.

Applicability in phase II: The exact quantum of unallocated power that would be made available for bundling with solar power during phase II would be ascertained by the Ministry of Power (MoP), which has the mandate to allocate the unallocated power to high power-deficit states. However, it is unlikely that after the allocation of 1000 MW during phase I, sufficient unallocated power would be available to support the entire capacity targeted under phase II of the JNNSM.

At the same time, the 1:1 ratio of solar to thermal capacity (in MW) may not be required now as the solar tariff has fallen substantially during the last two years. As per estimates, bundling of conventional solar power with thermal power could be in the ratio of 2:1 to arrive at a tariff of about Rs 5.5 to Rs 6 per unit for the bundled power. But even with this reduced dependence on thermal power, the bundling scheme could have limited scope, since conventional power from the unallocated central pool is in very short supply.

Generation-based incentives

The generation-based incentive (GBI) was another mechanism introduced for developers of solar power. This was introduced to ensure the deployment of grid-connected solar power on a MW scale throughout the country, and to give a thrust to rooftop PV and other small solar power plants connected to distribution networks at voltage levels below 33 kV. The GBI was calculated as the difference between the tariff determined by the Central Electricity Regulatory Commission (CERC) or State Electricity Regulatory Commission (SERC), and the base rate of Rs 5.50 per kWh (for the FY 2010-11) escalated by 3 per cent every year. These projects will be selected based on a two-tier approach—first, pre-registration by states and thereafter, selection through a Web-enabled process on a first-come-first served basis.

Applicability in phase II of JNNSM: Unlike in phase I, the GBI in phase II is expected to be very low. Going by the calculations above, the preferential tariff for solar PV technology approved by CERC and various SERCs is in the range of Rs 9-11/kWh. As per the CERC draft tariff order for determining a levelled tariff for solar technology in 2013-14, the tariff for solar PV has further come down to Rs 8.75 per unit. Considering the current base rate of Rs 6/unit, MNRE will provide a GBI of Rs 2-3 per unit, which is considerably lower than the GBI provided during phase I. Despite the lower GBI, solar power developers can still avail the benefits for whatever they are worth.

Also, there are certain preconditions to avail GBI. As mentioned in the policy draft, only those states that were not covered under the Batch I scheme would be eligible for GBI. Projects for which GBI will be available will be connected to the 33kV grid and below. Also, the size of projects will be in the range of 500 kWp to 2.5 MWp, and capacity can increase in multiples of 500 kW only.

Viability gap funding

While both bundling and GBI have limited scopes in phase II of the JNNSM, the viability gap funding (VGF) scheme will be an attractive alternative to support solar projects. This scheme provides financial support in the form of grants, one-time or deferred, to infrastructure projects undertaken through public-private partnerships. Under this option, bidders would bid for VGF requirements in Rs/MW terms and the bidder with the minimum VGF requirement will be selected.

Through VGF, the government plans to make socially viable projects commercially viable. The government will provide VGF of up to 20 per cent of the total project cost. The government or statutory entity that owns the project may, if it decides so, provide additional grants out of its budget up to the 20 per cent of the total project cost.

If VGF is provided as an upfront capital assistance, there could be a possibility that project developers would bid aggressively, ignoring the long-term plant performance. This would be detrimental for the success of JNNSM. Therefore, disbursement of VGF would be done in multiple stages from the selection of the project. VGF payment will be subject to compliance to strict project performance parameters, which will be specified before awarding a project.

VGF will be provided in three stages:

25 per cent at the time of delivery of at least 50 per cent of the major equipment at the site. This will be based on the total procurement cost.

50 per cent on the successful commissioning of the full capacity of the plant.

Balance 25 per cent after one year of operations, as the project must meet requirements of generation as per guidelines.  

Broad outlines for generation-based incentive scheme 
  • Only states that were not covered under the Batch I scheme would be eligible.
  • The project will be connected to the 33kV grid and below.
  • The size of projects will be in the range of 500 kWp to 2.5 MWp, and capacity can increase in multiples of 500 kW only.
  • Maximum number of projects permitted from a state can be up to the capacity required for meeting solar RPO (renewable purchase obligation) targets at a rate of 0.25 per cent of the energy consumption for that state, with minimum and maximum capacities of 1.0 MW and 5.0 MW, respectively.
  • Selection of projects would be done by the Solar Energy Corporation of India on the basis of the discounts to be offered by project developers on the CERC or SERC-approved applicable tariff, whichever is lower.
  • GBI shall be payable to the purchasing utilities for a period of 12 years from the date of commissioning of the project.
  • SECI will be designated as the‘programme administrator’ by MNRE for administering the programme.

Electronics Bazaar, South Asia’s No.1 Electronics B2B magazine

- Advertisement -

Most Popular Articles

Motul India And Zypp Electric Start EV Repair Training For Mechanics

0
The initiative seeks to educate more than 10,000 mechanics on skills for maintaining and repairing electric vehicles. Automotive lubricant maker Motul India has partnered with...
Defence tech-India Israel

Israel Unveils New Initiative IAI Neusphere For Deeper Defence Tech Ties With India

0
IAI has been actively involved in India across various domains, including advanced radars and airborne warning and control systems for the Indian Air Force. Israel...

Amit Bhardwaj Appointed CFO Of Battery Smart

0
Leveraging 20+ years of experience to support India’s electric mobility revolution, Amit Bhardwaj joins Battery Smart as its new CFO to drive financial and...

Wardwizard Partners With Ampvolts To Boost EV Charging Network

0
Wardwizard will select strategic sites for establishing EV charging stations, while Ampvolts will provide the necessary EV charging equipment. Wardwizard Innovations & Mobility Ltd, an...

US Government Backs BAE, Rocket Lab With $60M

0
To accelerate semiconductor production for jets and solar cell manufacturing, the US Commerce Department is set to award $60 million in subsidies to BAE...

“We Bring Intelligence Early On Into The Design Cycle” – Michel Van Cotthem VP...

0
With a solution embedding intelligence early in the design-to-source lifecycle, Supplyframe aims to leverage India’s electronics manufacturing boom. At IEW 2024, Michel Van Cotthem...
Vijai Karthick Selvam, Director of Teqtis

“We Do Everything From The Initial Concept To The Final Box Build” – Vijai...

0
Why are testing and R&D essential to combat printed circuit board manufacturing challenges? Speaking to EFY's Nitisha Dubey, Vijai Karthick Selvam, Director of Teqtis,...
Abhishek Malik, Executive Director, Calcom Vision Ltd

“India’s Electronics Sector Is Growing Rapidly, Making This The Decade For Investors To Engage”...

0
From the complexities of manufacturing and sourcing components to testing processes that drive innovation, know all the exciting dynamics shaping this ever-evolving industry in...
Sunit Kapur, CEO of Epsilon

“Epsilon Leads With Low-Carbon Graphite Manufacturing, Outpaces Chinese Competitors” – Sunit Kapur, CEO of...

0
Are LFP cathodes and silicon-graphite anodes the best for cost efficiency in EV batteries? Sunit Kapur, CEO of Epsilon Advanced Materials, discusses this with...
John W. Mitchell, President and CEO, IPC

“India’s Core Focus On 5G, IoT, AI Fosters Need For Advanced Electronics,Components, And Semiconductors”...

0
Will Industry 4.0 supercharge India’s progress in semiconductor and electronics manufacturing? IPC President and CEO John W. Mitchell shared more strategies on the country’s...

HKTDC Electronics Fair Sparks Innovation, 60,000+ Participants!

0
Showcasing cutting-edge tech, global innovation, and booming markets for the future of electronics, HKTDC’s Hong Kong Electronics Fair and electronicAsia drew 60,000+ professionals. Last month,...
Applied Materials Representational Image

Applied Materials Selects Six Startups For Deep-Tech Accelerator Programme

0
The selected deep-tech startups will be evaluated for investment by Applied Ventures and potential collaboration opportunities with Applied Materials. In collaboration with the company's India...

Space tech Startup Akash Secures $68M CHIPS Funding

0
Eyeing to power into AI, EVs, and more high-tech industries, Akash Systems lands $68 million CHIPS grant to boost its cooling tech facility, generating...

Wireless Light-Based Communication With Velmenni’s Technology

0
Velmenni is at the forefront of wireless communication innovation with its pioneering light-based technologies, Li-Fi and LC Link. Founded by Deepak Solanki in October 2014...

Harnessing AI Technology For Efficient Pest Management

0
AI-Genix, an agri-tech startup, is transforming pest management for farmers through advanced AI-enabled systems that precisely target harmful pests. In an industry where pesticides and...

Industry's Buzz

Motul India And Zypp Electric Start EV Repair Training For Mechanics

0
The initiative seeks to educate more than 10,000 mechanics on skills for maintaining and repairing electric vehicles. Automotive lubricant maker Motul India has partnered with...
Defence tech-India Israel

Israel Unveils New Initiative IAI Neusphere For Deeper Defence Tech Ties With India

0
IAI has been actively involved in India across various domains, including advanced radars and airborne warning and control systems for the Indian Air Force. Israel...

Amit Bhardwaj Appointed CFO Of Battery Smart

0
Leveraging 20+ years of experience to support India’s electric mobility revolution, Amit Bhardwaj joins Battery Smart as its new CFO to drive financial and...

Wardwizard Partners With Ampvolts To Boost EV Charging Network

0
Wardwizard will select strategic sites for establishing EV charging stations, while Ampvolts will provide the necessary EV charging equipment. Wardwizard Innovations & Mobility Ltd, an...

US Government Backs BAE, Rocket Lab With $60M

0
To accelerate semiconductor production for jets and solar cell manufacturing, the US Commerce Department is set to award $60 million in subsidies to BAE...

Learn From Leaders

“We Bring Intelligence Early On Into The Design Cycle” – Michel Van Cotthem VP...

0
With a solution embedding intelligence early in the design-to-source lifecycle, Supplyframe aims to leverage India’s electronics manufacturing boom. At IEW 2024, Michel Van Cotthem...
Vijai Karthick Selvam, Director of Teqtis

“We Do Everything From The Initial Concept To The Final Box Build” – Vijai...

0
Why are testing and R&D essential to combat printed circuit board manufacturing challenges? Speaking to EFY's Nitisha Dubey, Vijai Karthick Selvam, Director of Teqtis,...
Abhishek Malik, Executive Director, Calcom Vision Ltd

“India’s Electronics Sector Is Growing Rapidly, Making This The Decade For Investors To Engage”...

0
From the complexities of manufacturing and sourcing components to testing processes that drive innovation, know all the exciting dynamics shaping this ever-evolving industry in...
Sunit Kapur, CEO of Epsilon

“Epsilon Leads With Low-Carbon Graphite Manufacturing, Outpaces Chinese Competitors” – Sunit Kapur, CEO of...

0
Are LFP cathodes and silicon-graphite anodes the best for cost efficiency in EV batteries? Sunit Kapur, CEO of Epsilon Advanced Materials, discusses this with...
John W. Mitchell, President and CEO, IPC

“India’s Core Focus On 5G, IoT, AI Fosters Need For Advanced Electronics,Components, And Semiconductors”...

0
Will Industry 4.0 supercharge India’s progress in semiconductor and electronics manufacturing? IPC President and CEO John W. Mitchell shared more strategies on the country’s...

Startups

HKTDC Electronics Fair Sparks Innovation, 60,000+ Participants!

0
Showcasing cutting-edge tech, global innovation, and booming markets for the future of electronics, HKTDC’s Hong Kong Electronics Fair and electronicAsia drew 60,000+ professionals. Last month,...
Applied Materials Representational Image

Applied Materials Selects Six Startups For Deep-Tech Accelerator Programme

0
The selected deep-tech startups will be evaluated for investment by Applied Ventures and potential collaboration opportunities with Applied Materials. In collaboration with the company's India...

Space tech Startup Akash Secures $68M CHIPS Funding

0
Eyeing to power into AI, EVs, and more high-tech industries, Akash Systems lands $68 million CHIPS grant to boost its cooling tech facility, generating...

Wireless Light-Based Communication With Velmenni’s Technology

0
Velmenni is at the forefront of wireless communication innovation with its pioneering light-based technologies, Li-Fi and LC Link. Founded by Deepak Solanki in October 2014...

Harnessing AI Technology For Efficient Pest Management

0
AI-Genix, an agri-tech startup, is transforming pest management for farmers through advanced AI-enabled systems that precisely target harmful pests. In an industry where pesticides and...